Monday, November 11, 2013

Breaking Ground

The cold grey skies and a few rain drops were not enough to stop the celebration at Circle High School's Ground Breaking Ceremony. Superintendent Jim Johnson addressed those gathered, the band struck up and the cheer team put their best foot forward. Circle High Students then donned hard hard hats and shoveled the first dirt in preparation for their new school. 

Circle High School Gathers Under Greying Skies

Superintendent Jim Johnson 

Circle Students Officially Break Ground on Their New School

A few days later, the sun broke through and excavation crews moved a lot of ground...

Removing Existing Parking lot

Building Pad Construction

Building Pad Construction

Tennis Court Grading


Thursday, October 24, 2013

Circle High School Phasing

                                              

Phase 1 of construction consists of the site development package.
Work includes site excavation, grading, tennis courts and site electrical.
                                              

Phase 2 of construction consists of partial building construction.
Work includes construction of three education wings and new competition gym.
                                              

Phase 3 of construction consists of partial building construction and demolition.
Work includes demolition of existing media center, classrooms and gymnasium,
and construction of administration area, media center and black box.
                                              

Phase 4 of construction consists of partial building construction and demolition.
Work includes demolition of remaining existing building and
remodel of entrance to existing auditorium.