Wednesday, August 28, 2013

Thursday, August 22, 2013

First Week of School

South Wing Building Pad 

Footing Installation on the East Wing (This will be the North Wall.)

Poured Footings on the East Wing (This will be the East Wall.)

Students Under Construction! Safety First!

Thursday, August 8, 2013

In Phases

Driving by Circle Oil Hill Elementary, you may notice things are changing, but not all at once. The construction and remodel will take place in phases, allowing for learning as usual with the least disruption possible.
Phase 1: Addition of classrooms to South and East wings.

Phase 2: Interior remodel and additions. 

Phase 3: Final interior remodel.

Before School Starts

As teachers and students prepare for the first day of school, Simpson Construction crews are hard at work making sure everything and everyone will be safe this year. Phase One of construction is well underway, despite the rain and mud:

Fencing and Signage is up. Concrete reinforcing is being tied together for footing installation.

The portable has been moved to allow room for South Wing construction.

Lots of rain South of the building where six classrooms will be added.

Two classrooms will be added on the East.