Tuesday, July 29, 2014

Gymnasium High Walls

East Gymnasium High Wall Erection



West Gymnasium Walls



Weight Room & Cardio Room Structure 

Wednesday, July 16, 2014

Goings-on at Circle High School

Classroom Wing Interior Framing

Classroom Wing Exterior with Waterproofing Coat Installed

Field House Steel Erection

Gym Truss Fabrication

Locker Room Remodel

Roofing Installation 



Walking Track Floor Poured

Happenings at Oil Hill

New Administration Wing and North Canopy

Flex Room Drywall Installation

Millwork Installation
Bathroom Tile Installation

Kitchen Equipment Installation

Trash Enclosure

Thursday, June 26, 2014

Busy Summer

Construction of the Classroom Wings

Framing inside one of the Classroom Wings

Classroom Wing Steel Erection

Installation of the Gymnasium Pre-cast Panels


Installation of Bleacher Risers


Thursday, June 19, 2014

Summer at School

Framing of the East Flex Room

Future Speech & Psychology Room

Teachers' Dining Room

Millwork in the Teachers' Workroom

Installation of the North Canopy

Tuesday, June 10, 2014

A View from Above

Special thanks to Chris Callen from Builders Plus Concrete for these awesome aerial photos of Circle High School!





Be sure to visit the Builders Plus Concrete Website and check out their time-lapse video from a previous project!

Friday, June 6, 2014

Progress Despite the Rain

Classroom Wing Framing

Classroom Wing Steel

Installation of Exterior Sheathing

Gym Pre-Cast Panel Installation

Locker Room ready for Renovations