| Area A (East) Classroom Additions |
![]() |
| Area A Roofing |
![]() |
| Area B (South) Classroom Addition |
![]() |
| Area B Sloped Roof Installation |
![]() |
| Brick Installation on East Addition |
![]() |
| Ductwork Installation |
![]() |
| Interior Wall Framing & Rough In |
![]() |
| Phase 1: Addition of classrooms to South and East wings. |
![]() |
| Phase 2: Interior remodel and additions. |
![]() |
| Phase 3: Final interior remodel. |
![]() |
| Fencing and Signage is up. Concrete reinforcing is being tied together for footing installation. |
![]() |
| The portable has been moved to allow room for South Wing construction. |
![]() |
| Lots of rain South of the building where six classrooms will be added. |
![]() |
| Two classrooms will be added on the East. |