Actually, it's a concrete truck pouring footings for the South Wing Classrooms. |
Wednesday, August 28, 2013
Thursday, August 22, 2013
First Week of School
Thursday, August 8, 2013
In Phases
Driving by Circle Oil Hill Elementary, you may notice things are changing, but not all at once. The construction and remodel will take place in phases, allowing for learning as usual with the least disruption possible.
Phase 1: Addition of classrooms to South and East wings. |
Phase 2: Interior remodel and additions. |
Phase 3: Final interior remodel. |
Before School Starts
As teachers and students prepare for the first day of school, Simpson Construction crews are hard at work making sure everything and everyone will be safe this year. Phase One of construction is well underway, despite the rain and mud:
Fencing and Signage is up. Concrete reinforcing is being tied together for footing installation. |
The portable has been moved to allow room for South Wing construction. |
Lots of rain South of the building where six classrooms will be added. |
Two classrooms will be added on the East. |